Time and Work

1.If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

यदि A और B मिलकर किसी कार्य को 15 दिनों में तथा B अकेले 20 दिनों में पूरा कर सकते हैं, तो A अकेले उस कार्य को कितने दिनों में पूरा कर सकता है?

A.60

B.45

C.40

D.30

Answer: Option A

Solution:1st method:

A and B complete a work in = 15 days

One day’s work of (A + B) = 1/15

B complete the work in = 20 days;

One day’s work of B = 1/20

Then, A’s one day’s work =1/15−1/20

=4−3/6

=1/60

Thus, A can complete the work in = 60 days.

2nd method:

(A + B)’s one day’s % work =100/15

= 6.66%

B’s one day’s % work =100/20

= 5%

A’s one day’s % work = 6.66 – 5 = 1.66%

Thus, A need =100/1.66

= 60 days to complete the work.

2. If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:

यदि A और B मिलकर एक काम को 18 दिनों में पूरा कर सकते हैं, A और C एक साथ 12 दिनों में, और B और C एक साथ 9 दिनों में पूरा कर सकते हैं, तो B अकेले उस काम को कितने दिनों में पूरा कर सकता है:

A. 18 days

B. 24 days

C. 30 days

D. 40 days

Answer: Option B

Solution: One day’s work of (A+B) =1/18……(1)

One day’s work of (A+C) =1/12…….(2)

One day’s work of (B+C)=1/9…….(3)

Adding (1), (2) and(3)

2× (A+B+C) =1/18+1/12+1/9

2(A+B+C) =1/4

One day’s work of

A+B+C=1/8

B=1/8− (A+C)

B=1/8−1/12

One day’s work of B=3−2/24

=1/24

Bneed24days

3. A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

A और B मिलकर एक कार्य को 3 दिनों में पूरा कर सकते हैं। वे एक साथ शुरू करते हैं लेकिन 2 दिनों के बाद, B ने काम छोड़ दिया। यदि कार्य दो दिन बाद पूरा हो जाता है, तो बालोने कार्य कर सकता है

A. 5 days

B. 6 days

C. 9 days

D. 10 days

Answer: Option B

Solution:1st Method:

(A+B)’s one day’s work =1/3 part

(A+B) works 2 days together =2/3part

Remaining work =1−2/3

=1/3 part

1/3 part of work is completed by A in two days

Hence, one day’s work of A =1/6

Then, one day’s work of B =1/3−1/6

 =1/6

So, B alone can complete the whole work in 6 days.

2nd Method:

(A+B)’s one day’s % work =100/3

= 33.3%

Work completed in 2 days = 66.6%

Remaining work = 33.4%

One day’s % work of A =33.4/2

= 16.7%

One day’s work of B = 33.4 – 16.7 = 16.7%

B alone can complete the work in,

=100/16.7

= 5.98 days

≈ 6 days.